Question:

It's great that Grand Avenue is open now, but why is the road still extremely bumpy? There are still potholes from 9th to 13th that are terrible to drive over.

Answer:

"The project in question involved the replacement of two water mains (16" and 30" in diameter) between 13th and 15th on Grand Avenue. There was no work performed between 9th and 13th and the roadway was patched only in areas of disturbance. Grand Avenue is a state highway and the roadway surface falls under the jurisdiction of the Wyoming Department of Transportation (WYDOT). WYDOT will be improving Grand Avenue between 3rd and 15th in 2019. The project includes a mill and asphalt overlay, selective curb and gutter replacement, ADA ramps, and new traffic signals."

Ask the City Of Laramie is your chance to send the city that burning question that you have always wondered about such as: “Where can I get a city parking permit?” or “Why did my water usage rates go through the roof?”

Please note that the City of Laramie will answer as many questions as possible at their discretion.

Ask The City Of Laramie

Complete the form below to submit your question to the City Of Laramie. Then check back later to see if your question is answered on Laramie Live. Please note that the city will post replies at its own discretion.
  • Name
  • Remain Anonymous?